Chronolog(tm) Capacity Manager
OverviewFeature tourBest practicesSubscriptionsSupport
The scheduling processExample workflowAdding an eventGeneral tips
Betabord(tm) Quality Assurance Manager

example


Don't slam your team! With a quick look at the Capacity of Entire Company report, you can decide whether to rush a sales prospect or take it easy to bring in work at a reasonable rate.


Subscriber login | Contact us


A service of Arlo Leach
Copyright © 2004-24, all rights reserved


Example workflow

To illustrate some of the differences between Chronolog and other scheduling tools, here's an example of what a project manager might do to schedule a new task:

  1. A client requests a few changes to a recently released product. The project manager discusses the changes with a technology manager and establishes a time estimate of 12 hours to complete the work.

  2. The project manager views the Capacity of Individual Users report, selecting all the developers on the team.

  3. The report shows that in two weeks, one of the developers has two tasks and a meeting scheduled, for a total of 17 hours, with 13 hours free (that particular developer is on a 4-day schedule with 30 available hours per week, leaving two hours for unscheduled admin time).

    (click to enlarge)

  4. The project manager schedules the 12 hour task for that entire week, and tells the client it will be finished by the end of that week. The developer now has three tasks scheduled for that week, nearly totaling the developer's available time.

    (click to enlarge)

  5. As the developer works on the first task, it starts to take longer than expected, so the developer switches gears to the second task and finishes that one relatively quickly. The next day, the developer makes a fresh start on the first task and overcomes the previous day's obstacle. At the same time, the developer starts planning the third task.

  6. The project manager checks in at mid-week to make sure the developer is on target with all three tasks. Although the developer has been jumping around and spending a little more or less time than expected on each of the tasks, the developer's work for the week is on target overall. The project manager is satisfied and doesn't need to make any schedule adjustments.

  7. By the end of the developer's workweek, all three tasks are completed. The first two took 18 hours, and the third one took 10 hours, so the time estimates weren't exactly right. However, the developer's schedule was flexible enough to absorb the variances, and all the work was completed on time.